Curry Street construction update for July 2-6 in Carson City
Here is the construction update on the Curry Streetscape Project in downtown Carson City for July 2-6:
— Q&D will not be performing any construction activities on July 4 and all streets will be open on Wednesday only.
— There will be sewer work from Carson Street to Nevada Street on Musser, Proctor, Telegraph, Spear and Robinson and these streets will be closed throughout the week except for the holiday.
— Curry from Musser to Robinson will be closed for water service and there will be possible night work throughout the week.
— During the week, block-by-block, parking and streets will reopen as the construction activity moves north along Curry Street.
Days of closures are subject to change due to weather conditions.
Downtown businesses are open during construction. For a list of events visit VisitCarsonCity.com. Check out the construction map at www.carsonproud.com