NDOT contracts with SNC to resurface U.S. 50 in Eastern Carson City this July
The Nevada Department of Transportation recently approved a contract for a project this summer that will resurface approximately two miles of U.S. 50 between Asphalt Drive and Nichols Lane in eastern Carson City.
Contractor Sierra Nevada Construction, Inc. was selected for the approximately $300,000 project, scheduled for this July, to resurface the aging highway surface.
Drivers should anticipate lane and brief intersection closures when the road is resurfaced in July. Speed limits will intermittently be reduced as low as 35 mph through the work zone. While one lane in each direction will always remain available, drivers will be advised to use alternate nearby routes during construction. The construction schedule is subject to change.
Using the chip seal method, a 3/8-inch layer of new asphalt and roadway gravel will be placed and sealed with a top layer of oil. Often considered the best value for road maintenance dollar, the chip seal will restore roadway surface friction and aesthetics on the highway which was last fully repaved in 2004. It would cost as much as $3 million to fully repave the roadway including additional accessibility improvements.
SAFE WORK ZONE DRIVING TIPS
— Always buckle up.
— Use alternate routes through the work zone when possible
— Leave extra travel time when driving through the work zone
— Follow all posted work zone signage and speed limits
— Pay attention and minimize distractions.
— Keep a safe distance from cars ahead, traffic barriers, construction equipment and workers.
— Fines can be doubled for speeding in active road work zones
Plan ahead and give yourself time to reach your destination. Simply dial ‘511’ or log onto www.nevadadot.com before driving for a listing of Nevada highway construction.