Carson City area road report for week of Oct. 8-14
Here is the Carson City area road report for the week of Oct. 8-14, 2018. Work continues on the Downtown Curry Streetscape Project. This week's work will consist of:
— Ongoing Concrete work on Curry, Telegraph and Alley, Robinson and Spear Street.
— Sidewalk pavers ongoing on Curry, Telegraph to Robinson.
— Utility work on Musser and tie-ins in various locations.
— Lowering Utilities in various locations throughout the project.
There will be intermittent street closures during all these activities, detours will be signed. Parking will be limited in work areas. Beginning Oct. 15 Curry St. will be completely closed for milling and paving through Oct. 26.
For specific details regarding traffic impacts as a result of the project, please refer to www.carsonproud.com/ for more information. This source will be updated weekly throughout the duration of the project.
Road closure expected at the following location due to road and utility work:
— Clear Creek Avenue will be closed between Center Drive and Snyder Avenue, Monday through Sunday, all hours.
Lane restrictions are expected at the following locations due to road and utility work.
— I-580 will have intermittent lane closures between South Reno and Washoe Valley, Monday through Friday, 8:00 a.m. to 3:00 p.m.
— Fairview Drive will have intermittent lane closures between Roop Street and U.S. 50, Tuesday, 7:00 a.m. to 5:30 p.m.
— Kings Canyon Road will have reduces lanes between Custer Circle and Canyon Drive, Tuesday through Friday, 7:00 a.m. to 5:30 p.m.
— S. Edmonds Drive will have reduced lanes between Fairview Drive and Lompa Lane, Monday Through Saturday, 7:00 a.m. to 5:30 p.m.