Here is the South Carson Street project and Carson City area road report for the week of July 13-19, 2020. For information on lane restrictions and street closures related to the South Carson Street Project, please visit CarsonProud.com.
SNC crews continue to the roundabout installment phase of the project. The following streets will be impacted:
— 5th Street to Stewart St: one lane in each direction will be open, the cone zone will remain in place around-the-clock.
— 9th Street will be closed Monday, July 6.
— Stewart Street at the Carson Street intersection will open on Tuesday for traffic in both directions.
— Frontage Road is open to two - way traffic with a north driveway closure and temporary driveway closures.
— Roop Street: Northbound traffic only, Industrial Way to Fairview.
— Colorado Street to Stewart lane shift, cones will be in place.
— Fairview Drive: one lane in each direction will be open around – the – clock. Driveway closures as needed.
— Fairview to Appion: one lane in each direction, the cone zone will remain in place around-the-clock.
Snyder to Fairview will experience intersections closures:
Tues 7/14 – Roventini Way and Clearview Dr (one intersection closed at a time)
Wednesday 7/15 – Eagle Station Ln and Koontz Ln (one intersection closed at a time)
Thurs 7/16 – South driveway entrances for Frontage Rd
Fri 7/17 – Sonoma St and driveway entrances for Frontage Rd
Elsewhere, here is the Carson City area road report for the week. Closures are expected at the following locations due to road and utility work:
— Airport Road remains closed in both directions between Woodside Drive and Menlo Drive for installation of new sewer and water utilities. Airport Road will also be closed to through traffic between US 50 and Woodside Drive, Monday through Friday,7 a.m. to 5:30 p.m. Residential and business access will also be allowed. JAC service will continue; however, detours will be in effect.
— Livermore Lane and the Pete Livermore Sports Complex will be closed until further notice while the parking lot is reconstructed.
— Retail Court will be closed east of College Parkway, Monday through Friday, all day. Access to the businesses will be maintained. There may also be periodic closures and detours to the multi-use path between Emerson Drive and Retail Court.
Lane restrictions are expected at the following locations due to road/utility work:
— College Parkway will have a single lane closure in the westbound direction between the I-580 Interchange and Retail Court for construction associated with the adjacent development, Monday through Friday, 9 a.m. to 3 p.m. The lane closure may extend up the interchange off-ramps.
— Fairview Drive will have continued eastbound and westbound single lane closures while utility work and roadway reconstruction occurs, Monday through Friday, 7 a.m. to 5:30 p.m.